Kyrene School District
Portable Replacement Milestone Schedule
| |
Colina |
Esperanza |
Lagos |
Paloma |
Mariposa |
Cielo |
Niņos |
Sureņo |
|
Install construction fencing |
NA |
NA |
NA |
12/19/08 |
12/19/08 |
12/19/08 |
5/22/09 |
5/22/09 |
|
Start removing portables for new construction |
NA |
NA |
NA |
N/A |
NA |
3/27/09 |
5/26/09 |
N/A |
|
Start grading and utilities work |
12/15/08 |
1/19/09 |
2/2/09 |
3/2/09 |
4/9/09 |
4/30/09 |
7/13/09 |
6/22/09 |
|
Start building foundation |
1/17/09 |
2/16/09 |
3/9/09 |
4/2/09 |
4/18/09 |
5/22/09 |
8/10/09 |
7/6/09 |
|
Start delivering building components |
1/15/09 |
2/16/09 |
3/11/09 |
4/17/09 |
5/13/09 |
5/26/09 |
8/17/09 |
7/15/09 |
|
Buildings complete |
4/30/09 |
5/29/09 |
6/19/09 |
7/31/09 |
7/31/09 |
7/27/09 |
11/25/09 |
10/23/09 |
|
Remove remaining portables |
6/1/09 |
NA |
6/8/09 |
8/21/09 |
7/6/09 |
8/17/09 |
6/15/09 |
11/23/09 |
|